Design and build - pros and cons
Design and build is a term describing a procurement route in which a single contractor is appointed to design (or complete the design) and then to construct the works. This is as opposed to a traditional contract, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.
Design and build can be advantageous in terms of time as it allows the overlap of design and construction reducing the overall project delivery time.
The fact that there is a single point of responsibility for the client to deal with once the contract is awarded can also make things simpler. The client is also able to engage with the contractor and their design team or supply chain earlier in the design process to try and achieve a more practical or buildable solution if necessary.
In terms of cost, it allows the client a certain amount of control as the contractor generally agrees to take on responsibility for the design and construction for a pre-agreed price. This means that the contractor takes on much of the financial risk (which may be reflected in the price). However, as the contractor is responsible for the design, they may make cost savings here (which can impact on quality).
Under some design and build contracts, the design team will be novated to the contractor, which can benefit quality (ie they transfer from working for the client to working for the contractor). This can be beneficial to the client as it maintains continuity between pre-tender and post-tender design whilst leaving sole responsibility for designing and building the project with the contractor. However, it can leave them without suitable independent advisors to help them oversee the developing design and then the construction. For more information, see Novation.
There are some disadvantages to the design and build procurement route. In terms of quality, the contractor may exploit a specification that is open to interpretation and choose the cheapest route. This can mean that quality may be compromised if the employer’s requirements do not adequately ensure the anticipated specifications are adhered to.
There is also the risk that the client may have to pay more if the contractor has to take on an unreasonably high level of risk due to a lack of design clarity when tendering. In terms of design flexibility, it is also important to consider that any request for changes will have cost and time implications.
[edit] Related articles on Designing Buildings
- Construction contract.
- Construction management contract.
- Design and build.
- Design build operate (DBO).
- Design build operate maintain DBOM.
- Design liability.
- Employer’s requirements.
- JCT Design and Build Contract.
- Management contracting - pros and cons.
- Novation.
- Procurement route.
- Traditional contract - pros and cons.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments